Project Overview

Bergen County and Essex County are advancing the design for the replacement of the existing Kingsland Avenue (Avondale and De Jessa Memorial) Bridge over the Passaic River to address its structural deficiencies and maintain an important transportation connection for local residents and regional commuters in Bergen County and Essex County. Due to its age, the bridge has deteriorated over time and routine maintenance can no longer address the deficiencies.

Overall Project Schedule by Phases

  • Local Concept Development Study โ€“ completed Spring 2020
  • Local Preliminary Engineering Phase โ€“ current, Summer 2022 โ€“ Spring 2024
  • Final Design Phase โ€“ anticipated Summer 2024 โ€“ Summer 2026
  • Construction Phase โ€“ anticipated Fall 2026 โ€“ Spring 2028

Local Concept Development Study Phase

A Local Concept Development (LCD) Study for major rehabilitation or replacement of the Kingsland Avenue Bridge was completed in 2020 using federal funding through the North Jersey Transportation Planning Authority (NJTPA), with Bergen County as the project sponsor and Essex County with shared jurisdiction. During this phase, a well-defined Purpose and Need Statement was developed focusing on the need to improve safety and maintain the current crossing over the Passaic River. A number of conceptual alternatives were developed to meet the project goals and objectives.

In coordination with the NJTPA, NJDOT, FHWA, local officials, community stakeholders, and permitting agencies, it was agreed, upon completion of an alternatives analysis, that the recommended Preliminary Preferred Alternative (PPA) to address the structural deficiencies is to replace the bridge with a new bridge structure. Resolutions of Support were passed by both the Township of Lyndhurst and Township of Nutley for the PPA. Improvements to the approach roadway intersections are also proposed in the vicinity of the bridge in Lyndhurst and in Nutley to better accommodate vehicular flow and mobility for pedestrians and bicyclists.

Local Preliminary Engineering Phase

The project is currently in the Local Preliminary Engineering (LPE) phase. The LPE phase involves performing engineering and environmental tasks and documentation in order to obtain National Environmental Policy Act (NEPA) clearance for the project. Based on the Preliminary Preferred Alternative (PPA), a number of activities are simultaneously set in motion: community involvement (meetings with affected property owners or business owners), agency consultation, environmental documentation, design level mapping and design services. To inform and to encourage community consensus, community stakeholder and public information center meetings will be conducted, which may lead to minor refinements of the approach roadway intersections of the PPA. The Townships of Lyndhurst and Nutley will be asked to maintain the resolutions of support for the PPA and for any design refinements.

The tasks conducted during the LPE Phase consist of, but are not limited to:

  • Technical Environmental Studies (including Section 106 and Section 4(f) Evaluation)
  • NEPA Document (Categorical Exclusion)
  • Development of design level base plans
  • Utility discovery and verification
  • Geotechnical studies for foundation and pavement design
  • Preliminary drainage work
  • Structural studies that document the structural selection process and the recommended structure and aesthetic treatments
  • Access and right of way impact evaluation
  • Development of property acquisition cost estimates and project cost estimates

The LPE phase work began in August 2022 and will be completed by Spring 2024.

LPE Phase โ€“ Anticipated Project Schedule (Major Milestones)
Environmental Documentation CompletedFall 2023
Submission of Local Preliminary Engineering ReportFall 2023
Completion of Local Preliminary Engineering PhaseSpring 2024
LPE Phase – Anticipated Community Involvement Schedule
Local Officials MeetingsFall 2022, Fall 2023/Winter 2024
Community Stakeholders MeetingSpring 2023
Public Information Center MeetingFall 2023/Winter 2024

Final Design and Construction Phases

There are two more phases to the Local Capital Project Delivery Process using federal funding to replace the bridge. The duration of the subsequent Final Design and Construction phases is to be determined in the future.

Local Capital Project Delivery Process

Purpose & Need Statement

Data Collection & Environmental Screening Report

Selection of Preliminary Preferred Alternative

Concept Development Report

NEPA Classification

Create Design Communications Report

Initial Public Outreach & Involvement

Approved Design Exception Report

Cost Estimates (Final Design, ROW & Construction)

Approved Environmental Document

Approved Project Plan

Preliminary Engineering Report

Update Design Communications Report

Continued Public Outreach & Involvement

Construction Contract Documents & PS&E Package

Environmental Reevaluations

Environmental Permits

Acquisition of ROW

Update Design Communications Report

Continued Public Outreach & Involvement

Implement and Complete Construction

Continue Public Outreach

As-Builts

Update and Finalize Design Communications Report

Close-out Documentation

Recent News

Update: May 23, 2024

Meeting Report for Public Information Center (PIC) Meeting No. 1 is now available

Update: February 29, 2024

Thank you to those who were able to attend the Public Information Center (PIC) Meeting No. 1 for the Local Preliminary Engineering (LPE) phase.

Update: January 24, 2024

Save the Date: Online Public Information Center for the Local Preliminary Engineering (LPE) phase

Translate ยป